Kingston Update November 2019

Here’s what’s been happening in Kingston & Kingston Coast

 

Kingston Village Shopping Centre & Grubb Rd Works

  • Roadworks are nearing completion with landscaping currently underway
  • Coastal Bvd expected to be operational end Nov 2019
  • Kingston Village Opening Day Celebrations December 4th 2019

 

Parkside Bvd (Heathwood) Basin:

  • Expected earthworks completion by end of November 2020
  • Landscaping pavements to commence early December 2020
  • Anticipate landscape completion April/May 2020

 

Kingston Coast Stage 1:

  • Final Council approval received for works to commence 18/10/2019
  • Construction works commenced as of 21/10/2019
  • Due to delayed commencement, weather permitting our revised expected construction completion is second quarter 2020
  • We anticipate titles to follow shortly after completion

Kingston Coast Stage 2:

  • We expect approval from all authorities by March 2020
  • Construction works expected to commence March 2020
  • Construction completion expected August 2020
  • We anticipate titles to follow shortly after completion approx Sept/October 2020