Coast Stage 1

  • Weather permitting, forecasted completion of construction early June 2020
  • Upon Statement of Compliance, soil testing and land valuations can be conducted
  • Titles forecasted end July 2020

 

Coast Stage 2

  • Anticipated commencement of construction works late June 2020
  • Stage 2 administration and construction pre-commencement phase has been impacted by Covid-19 shutdowns, therefore forecasted construction completion is now end of4thquarter 2020
  • Forecasted Titles 1st quarter 2021

 

“Parkside Bvd” Wetlands

  • Wetland planting has commenced, and general garden bed and trees planting is scheduled from 1st June 2020
  • Pergola construction is complete, with the timber boardwalk nearing completion
  • Footpaths are substantially completed, with one remaining section of footpath to be completed by 5thJune following completion of the timber boardwalk
  • Forecasted completion early June 2020
  • Pending Council approvals, we hope to open this Reserve to the public from mid-June 2020

 

“Splendour Walk” Wetlands

  • Targeted completion of civil earthworks clean-up, wetland shaping and topsoil is 3rdquarter 2020
  • Weather permitting, general landscaping works to commence shortly after earthworks, towards the end of 3rdquarter 2020
  • Due to the sensitivity of the Wetland plant species, final planting will likely be completed during 4thquarter 2020 in warmer weather.