Here’s what’s been happening in Kingston Ocean Grove & Kingston Coast
Coast Stage 1
- All sewer and stormwater drainage is complete
- Kerbing is complete
- Water services & gas services installation is complete
- Weather permitting, Electrical installation is set to commence shortly
- Weather permitting, forecasted completion of construction end May 2020
- Titles forecasted late 2nd Quarter
Coast Stage 2
- Engineering plans are still with COGG & Barwon Water. We are actively following up on approvals, however, this is yet to be received.
- Anticipated commence of construction works late April
- Due to delays in plan approvals, forecasted construction completion is now 4th quarter 2020
- Forecasted Titles 4th quarter 2020
“Parkside Bvd” Wetlands
- Wetland shaping and topsoiling is complete
- Some Wetland planting has commenced
- Footpaths are underway and nearing completion
- Weather permitting, forecasted completion early May 2020
“Splendour Walk” Wetlands
- Targeted completion of civil earthworks clean-up, wetland shaping and topsoil in the 2nd quarter 2020
- Weather permitting, general landscaping works to commence 2nd quarter 2020
- Due to the sensitivity of the Wetland plant species, this will likely be completed during 4th quarter 2020 in warmer weather.